Evolving electrical design requirements for renewables, battery storage and EV charging

Evolving electrical design requirements for renewables, battery storage and EV charging

With the rise of renewables, battery storage and electric vehicle charging, the demands on our electrical systems are evolving fast. Jonathan Swain, NAPIT Technical Writer, breaks down how contractors must adapt their designs and installations to stay compliant and safe.

The way we use electricity in our homes and businesses is changing rapidly. The rise of renewable technologies and electric vehicle supply equipment (EVSE) means that load profiles, even within domestic installations, may be significantly higher than ever before, and for much longer durations.

Greater care and consideration must now be taken during the design and installation of these systems, and contractors must evolve alongside the technology.

For example: your old college electrical lecturer may have taught you, when positioning circuit-breakers in a consumer unit, to place the highest-rated device next to the main switch and cascade down to the lowest.

Historically, this would have (mostly) been acceptable, as these circuits were rarely simultaneously and continuously loaded.

In today’s world, however, manufacturer’s instructions may now require devices to be suitably spaced to allow adequate heat dissipation within the consumer unit assembly and to ensure correct operation – particularly when installing systems to supply heat pumps, battery storage, EV charging equipment and solar PV.

These circuits will be drawing, or supplying, significant current for sustained periods, meaning breakers are likely to emit more heat in operation (I²R) than a circuit breaker supplying an average upstairs sockets circuit.

There is another crucial factor to consider; not only can these circuits present an increase in load – but also an increase in supply. Solar PV and battery storage systems deliver current into the installation, which has implications for how we select and erect systems to ensure they are suitably rated and not at risk of thermal damage.

What does BS 7671 say?

An often-overlooked change in Amendment 2 of BS 7671:2018+A2:2022 is an addition to Regulation 551.7.2, which outlines the requirements for installations where generating sets operate in parallel with other supply sources. Solar PV and battery storage systems operating alongside a primary DNO (Distribution Network Operator) supply fall within this regulation.

The new (fifth) indent states:

This regulation requires that the common parts of the installation shall be suitably rated for the combined current that could be simultaneously delivered by each supply source.

In electrical installations without parallel supplies (i.e. from generating sets, fed from a single point of supply), an upfront device typically provides overload protection to a consumer unit and ensures its rating cannot be exceeded. The presence of additional sources, unless correctly configured, could result in more current being delivered to connected loads, with a proportion bypassing the primary protective device and instead coming from the additional source.

Failure to account for this in design – resulting in non-compliance with the requirements of Regulation 551.7.2 – could compromise the intended protection of the installation. The potential consequence: thermal damage to an assembly now able to distribute more than its rated current (InA).

We will examine three illustrative scenarios showing the impact of the change through Regulation 551.7.2 being put into practice.

The intent is to raise awareness of these requirements, especially considering the growing prevalence of multi-source installations. The installations shown are relatively simple to highlight the core concept. In more complex installations, the designer will need to consider the implications across multiple points of an electrical system.

Scenario 1

A 100 A (InA) type-tested consumer unit is connected directly to a 100 A service fuse (In), with a final circuit connected to a 3.68 kW inverter with a 16 A design current (Ig).

In Fig 1, the rated current of the assembly could potentially be exceeded, making the installation non-compliant.

Potential solutions:

1. Install a distribution board rated at 116 A or more (InA). Some manufacturers have tested their 100 A assemblies and can provide a declaration of conformity along with instructions on how to achieve a 116 A conditional rating.

2. If the inverter or gateway has the facility, a Customer Limitation Scheme (CLS) could be provided. G100-compliant electronic control of the loads and supplies may ensure that the assembly rating is not exceeded.

3. If the installations maximum demand permits, an additional overcurrent protective device could be installed to reduce the In value. This would render the installation compliant; the calculation is now satisfied, as shown in Fig 2.

Scenario 2

In this example, an assessment of maximum demand shows that the full original supply capacity must always be maintained. Installing a switch-fuse isolator, as in Scenario 1, would reduce available current at certain times, i.e. when the PV system isn’t generating.

To resolve this, a dedicated renewables consumer unit has been installed, and the switch fuse repositioned, as shown in Fig 3. By installing the switch-fuse isolator, the assembly is sufficiently protected. The current demanded by the consumer unit cannot exceed its InA rating because of the overcurrent protection provided.

All parts of the system are suitably rated for the maximum potential current flow they will be subjected to. In this configuration there has been no loss of available capacity as the full 100 A is still available for distribution at the consumer unit.

Scenario 3

In previous scenarios, the consumer unit had the capacity to demand greater than its rated current due to the quantity and rating of the circuits connected.

As the combined capacity of the supplies could sustain this overload, the installation was non-compliant unless additional overcurrent devices were installed.

In Fig 4, however, we can see a similar arrangement – but the connected load has been reduced.

In BS 7671:2018+A2:2022+A3:2024, there is precedent that, under certain conditions, a device providing protection against overload does not necessarily need to be positioned at the start of an installation, as described in Regulation 433.2.2. It even permits the omission of devices for protection against overload where, because of the characteristics of the load or supply, an overload is unlikely or impossible, as described in Regulation 433.3.1[ii].

In this example, overload is not possible by design, protection is provided by the devices in the consumer unit itself. When this method is used to achieve compliance, appropriate labelling is required, as shown in Fig 5.

Conclusion

Some argue that the perceived risks described here would only arise if there were already a design failure, specifically, if a part of the installation were overloaded in breach of Regulation 433.1.1.

Whilst there may be a degree of truth in this view, it’s important to note that the regulation is a mandatory requirement, and no allowance is made for the application of diversity to meet its requirements. Diversity should never be used as a means of load control and/or overload protection regarding this regulation.

Note: Any intended (and documented) departure from BS 7671:2018+A2:2022+A3:2024 requires special consideration by the designer of the installation, and the resulting degree of safety shall not be less than that obtained by compliance with the Regulations.

In counter to the criticism: we’ve heard reports of contractors attempting to overcome supply capacity issues by installing microgenerators.

Installations evolve, and are added to throughout their service life and, as discussed, many emerging technologies can represent a significant increase in current demand.

In this light, perhaps even the harshest of critics can appreciate the intent and value of the regulation in the face of a rapidly evolving industry.

Traditional, linear supply arrangements are increasingly supplemented by additional sources.

Designers must now factor in new dimensions of current flow and protective coordination to ensure safe, compliant installations.